A handover with a date is a process with one conversation in it. Everything that goes wrong between a design and a build goes wrong because a decision was made by one side alone, and a single meeting at the end is where all of those decisions are discovered rather than made.

Rhona is working on a caseworker tool for a housing charity in Glasgow: two designers, three developers, and a previous project that generated 31 questions between the handover and the review.

Five things agreed before anything is drawn

Five agreements: names, breakpoints, token owner, state names, where the spec lives. None of them takes longer than a few minutes and all five are cheap to change on day one and expensive on day forty.

Before anything is drawn

Five agreements that bridge day one to day forty

Each takes minutes to settle up front and prevents translation mistakes or duplicate edits once code starts moving.

Day one before drawingwhen every naming and ownership rule is cheap to change
  1. 01Component namesagree whether it is card or tile so nobody translates in their head
  2. 02Breakpointsfix the exact widths where layout rules shift
  3. 03Token ownername one owner for shared values that change under both teams
  4. 04State namesshare the exact vocabulary for every component state
  5. 05Spec locationdecide one place where decisions live and stay updated
Day forty in the buildwhen mismatched terms and unowned changes cost double work

On the previous project, three words were used for one component across two teams, turning simple conversations into repeated translation.

Modular Type Scale & CSS Flex/Grid Motion Lab

Test harmonic typography ratios and live Flexbox/Grid layouts with 1-click CSS export.

Names first, because if the design says card and the code says tile, every conversation costs a translation, and the translation is done in somebody's head, differently each time. On the last project three words were in use for one component across two teams, and about a fifth of the questions were people establishing which thing was meant.

The token owner matters for a different reason: it is the one thing that will change under both teams during the build, and a change with no owner is a change made twice.

Three moments, and the one that gets dropped

Three moments: a kickoff, a review before the design is finished, and one before it ships. The first and the third are always scheduled, because one starts the work and the other approves it.

Three scheduled checks

The middle review is the one dropped and the one that saves the most

Kickoff and pre-ship reviews stay on the calendar, while the mid-design check is the only window where technical changes remain cheap.

  1. KickoffWork startsalways scheduled to align scope and initial agreements
  2. Mid-designReview before finishingabout sixty per cent complete: specific enough to assess, open enough to change
  3. Pre-shipFinal approvalalways scheduled, though expensive code decisions are already locked in

A developer in the design review prevents costly rewrites; a designer in the code review mostly observes work already built.

The middle review is the one that gets dropped and the one that saves the most. At about sixty per cent the design is specific enough to be assessed and unfinished enough to change, which is a window of about a week and the only point at which a technical objection is cheap.

The asymmetry that follows is worth stating: a developer in the design review is worth more than a designer in the code review. By the time there is code, the expensive decisions are made; by the time there is a design, they are still open.

Who decides what

The designer decides the appearance and the developer decides the implementation. That much is usually assumed and rarely contested.

Decision ownership

Appearance and code split cleanly, while behaviour sits in the middle

Friction rarely comes from layout or code structure. It comes from interactive edge cases where neither side wrote down who decides.

  • Designer owns appearance
  • Developer owns implementation
Behaviour decided by both
  • Designer owns appearancevisual hierarchy, spacing, typography, and layout intent
  • Developer owns implementationarchitecture, state wiring, and framework constraints

Slow connections, waiting controls, and optimistic actions carry both design consequences and technical constraints.

Behaviour is decided by both, and writing that down prevents most of the friction. What happens on a slow connection, what a control does while it is waiting, whether an action is optimistic: those are design questions with technical constraints and technical questions with design consequences, and the arguments about them are almost always arguments about who is allowed to decide.

Two things to measure

Log the questions, because each one is a gap in the process. Not a gap in the person asking: a question asked during a build is a decision that was not made, or was made and not written down, or was written somewhere nobody looks.

Two metrics from the build

Most build questions came from missing component states

Logging every handover question turned a vague complaint about friction into a specific count that changed the definition of done.

questions logged between handover and review

  1. Total questions loggedeach question marks a decision never made or never recorded31
  2. Questions about statesled directly to requiring empty, loading, error, and offline states for done19

Putting those four states into the definition of done moves them from accidental discoveries to required deliverables.

31 questions last time, and 19 of them were about states. That single number decided the next project's process, because it is a specific and fixable thing rather than a general sense that handovers are difficult.

Which is why done includes the empty, loading, error and offline states. Putting them in the definition of done moves them from something a developer discovers to something the work is not finished without.

What to open

A shared glossary in the repository is the first artefact, free, twenty lines, one term per line. It replaces two teams using three words for one component, and it is the cheapest thing on this page by a distance.

What to open first

Two free files replace memory and scattered chat threads

Keeping terms and answers inside the repository and issue tracker stops teams from answering the same question multiple times.

Informal trackingscattered across chats and heads
Shared team artefactsfree files living where the work lives
Component termsTwo teams using three words for one componentShared glossary in the repository, one term per line
Build questionsSame question answered four times across two chat toolsQuestion log inside the ticket with every answer recorded

When the fifth person wonders how a control behaves, they read the recorded answer instead of interrupting someone.

A question log in the ticket is the second, free, and it replaces answering the same question in four separate messages across two tools. Every question and its answer, in the place the work lives, so the fifth person to wonder finds the answer instead of asking.

Where it stalls: the handover is an event

A handover appears in a plan as a milestone with a date. Before it, design; after it, build. The word itself carries the model: something is handed from one pair of hands to another and the first pair lets go.

Where the process stalls

Treating handover as a single date cuts off the conversation too early

When one milestone implies design is done and the first pair lets go, dozens of edge cases get solved silently during the build.

Replacing the single handover date with three smaller milestones takes roughly two hours on the calendar.

What actually happens is that the second pair meets forty situations the first pair never considered, over six weeks, and resolves them alone because the process has no place for asking. The questions get asked anyway, in messages, at inconvenient moments, and the answers do not get written down anywhere.

Replacing the milestone with three smaller ones costs about two hours of calendar time and is the whole intervention.

What it looks like when it goes wrong

The previous project's design review had no developer in it. The design used a drag and drop reordering for a caseworker's daily list, which was the right interaction and could not be built accessibly in the framework the team was on without a fortnight of work nobody had. It was found in the build, the feature shipped with the drag and no keyboard alternative, and two of the charity's own caseworkers cannot use a mouse. They had been using a spreadsheet for eight months by the time it was noticed.

When a review misses the build

A clean design review hid an inaccessible interaction for eight months

Without a developer in the design review, an interaction shipped that could not support keyboard users in the chosen framework.

  • Drag-and-drop list reorderinglooked right on screen and shipped on schedule
What shipped to caseworkers
  • No developer in design reviewframework limitation stayed invisible until implementation
  • No accessible keyboard fallbackbuilding one would have taken a fortnight nobody had
  • Caseworkers forced onto spreadsheetstwo staff who cannot use a mouse worked outside the app for eight months

Shared specs for states, asset formats, and token ownership keep framework constraints visible while changes are still cheap.

The states that produced nineteen of the thirty one questions belong in a document with a fixed shape, which is sizes, states and behaviour written down. The files that cross with the design have their own naming and format agreements, which are exports, formats and naming. And the token owner named in the first agreement is doing a job that has a page of its own, which is contribution, versioning and drift. What else a handover owes is one level up, in everything a developer needs and usually is not given.